Upcoming:
I-75 will have multiple lane closures in both directions beginning March 26 and going until April 21. Lane closures will be nightly from 7 p.m. to 7 a.m.
Crews will work to shift one lane of northbound traffic onto the southbound side of I-75, which will allow this new traffic pattern to have three lanes of traffic in each direction, ODOT said.
On Dryden Road, the ramp from the road to I-75 north will be closed April 9 until July 2025 as part of the I-75 reconstruction plan.
A detour will be set up from Dryden Road to Northlawn Avenue to Springboro Pike (S.R. 741) to I-75 north.
Olentangy Drive Bridge will be closed between Bayside Drive and Barrett Drive from Monday, April 10th to Sunday, July 9th. as crews will be replacing a bridge.
A detour will go from Bayside Drive to Spinning Road to Barrett Drive.
New:
Crews will work on highway lighting on I-75 north between Little York Road and I-70 March 21 to March 23 from 7 p.m. to 6 a.m. which will result in lane closures.
Ongoing:
Lane closures on both sides of Woodman Drive between Kolmar Avenue and Burkhardt Road began on March 6 and will go until March 24. Between the hours of 8 a.m. to 4 p.m. daily, crews are working on a bridge.
The I-75 reconstruction project is estimated to be completed in the summer of 2025.
Visit the ODOT website and OHGO.com for further travel updates.